The Wichita City Council waived up to $5 million in late fees the city could be charging Wichita Water Partners for delays at ...
After more than a year of delays, the Wichita City Council has a new timeline and guidelines for the completion of its new ...
In its 2024 annual report, the EPA incorrectly said Wichita's water customers "now have a brand-new water treatment plant ...
Contractors working on Wichita’s new water treatment plant provided the first comprehensive update to the community on ...
Wichita's new $574 million water treatment plant is behind schedule and over budget, but has the makings of a landmark ...
Wichita City Council members are seeking more information on a report alleging the city waived millions of dollars in late ...
Delays in Wichita's new water treatment plant cost the city millions of dollars. A report by The Wichita Eagle says that the ...
Marstall, hired in recent weeks to replace longtime manager Robert Layton, insisted on Friday that the city would get money ...
WICHITA, Kan. (KSNW) — The commissioning of Wichita’s new water treatment plant has been delayed again. The City of Wichita said in a news release Wednesday that the delay is due to ongoing problems ...
Every-other-day watering restrictions may soon be a reality for Wichita Water customers. "Overall, we're focused on outdoor irrigation. You'd be able to water three days a week," Public Works Director ...
Hunter Adams, water source and purification superintendent for the city of Wichita Falls, will speak at 7 p.m. Nov. 3 in Room 127 in Bolin Science Hall at Midwestern State University. He will speak on ...
Work at Wichita's new water treatment plant is on hold because of mechanical failures. The $557 million project, which broke ground at 21st and Hoover in 2020, has been plagued with delays. Work at ...